Among the design assignments carried out in the specific sector by E.T.S. S.p.A. we mention:

  • 2020 to now  – DATA 4 ITALY – Building DC05; Power IT = 4MW – (configuration N+1). Total amount of designed works (UPS rooms, batteries and transformation cabins): € 3.500.000,00.
  • 2019 ST Microelectronics – Agrate plant (MB) – Power IT = 360kW – Certification TIER III (configuration 2(N)). Total amount of designed works (UPS rooms, batteries, server rooms with 3 POD): € 900.000,00.
  • 2019 Istituto Poligrafico Zecca dello Stato IPZS di Foggia – Poower IT = 480kW – Certification TIER III (configuration 2(N)) – Solution with container. Technical support to Schneider Electric for the offer with the development of general electrical single-line diagrams, cabin layouts and technical rooms. In construction phase with the development of the construction solution of the transformer cabins, of the electrical panel rooms, the cable distribution and the electrical interconnections.
  • 2018 – 2019 DATA 4 ITALY – Building DC04; Power IT = 3MW – (configuration N+1). Total amount of designed works (UPS rooms, batteries and transformation cabins): € 2.300.000,00.
  • 2018 HUMAN TECHNOPOLE – Solution DC in container; Power IT = 90kW – (configuration 2N). Technical support to Schneider Electric for the offer with development of the layout inside the container which includes UPS, batteries, general panel, IT rack and special control and safety systems. In construction phase with the development of the general layout for the preparation of cable routes for future expansion up to a total of 10 containers.
  • 2017 – 2018 CISCO – CED of Vimercate (MI); Power IT 80kW – Preliminary and executive design for implementation of the existing configuration of UPS CED and Laboratories: Total amount of designed works: € 150.000,00.
  • 2016 – 2017 SUPERNAP – SIZIANO (PV) Certification Uptime TIER IV. Technical support to Schneider Eletric for the offer with the development of general electrical and supervision single-line diagrams and during the implementation phase with the drafting of signal interconnection diagrams between UPS, QGBT general panels, medium voltage panels and batteries.
  • 2016 – 2017 CRIF – Technological Pole; Power IT = 481kW – Certification Uptime TIER IV (configuration 2(N)). Construction design and assistance during the construction and certification phase of electrical systems (MV / LV substations, generator sets, UPS, batteries, lighting and motive power, connections to mechanical and control user equipment), special systems (smoke detection, anti-flooding, shutdown gas, fuel supply leakage control) and mechanical systems (hydronic air conditioning system, humidity control, ventilation system, post discharge extraction systems, condensate discharge); Total amount of designed works: approx. € 9,800,000.00.
  • 2015 DATA 4 ITALY – Building DC03; Power IT = 2,7MW – Certification TIER IV (configuration 2(N)). Total amount of designed works (UPS rooms, batteries and transformation cabins): € 2.800.000,00.
  • 2014 DATA 4 ITALY – Building DC02; Power IT = 4,2MW – Certification TIER III (configuration 2(N+1)). Total amount of designed works (UPS rooms, batteries and transformation cabins): € 4.500.000,00.