NAPLES AND SALERNO COLD IRONING

ongoing

The project concerns electrification works to the quays of the Ports of Naples and Salerno. The electrification of the berths is carried out by installing several outlet points and a prefabricated electrical substation housing all the necessary equipment to achieve a maximum power of 20 MVA.
ETS carried out the construction design.

ACTIVITY: Electrification Works to the quays of the Ports of Naples, Salerno and completion works

PLACE: Naples-Salerno, Italy

CUSTOMER: AdSP (Port System Authority) of the Central Tyrrhenian Sea

YEAR: 2024-ongoing

COST OF WORKSI: € 46.752.131,70